Rajuk Plan Approval Service in Dhaka, Bangladesh
Level Seven Architecture & Construction | Location: Banani, Dhaka | Phone: +8801714302055 | Service area: Dhaka, Bogra, Rajshahi, Rangpur, Mymensingh, & other regions of Bangladesh.
Any building constructed within Rajdhani Unnayan Kartripakkha's (RAJUK) jurisdiction, covering roughly 1,528 square kilometers under the DAP: 2022–2035 requires formal approval before construction can legally begin. Level Seven Architecture & Construction manages this process end-to-end for clients in Dhaka, handling document collection, drawing preparation, and submission through RAJUK's Electronic Construction Permitting System (ECPS).
RAJUK approval happens in two main stages:
1. Planning Permit (Land Use Clearance / LUC) Submitted online through Form-101, this step confirms the land's approved use before any building design is finalized. Required documents typically include the land registry, mutation records, national ID, updated land tax receipts, and a digital land survey. The standard processing time is around 30 days, and an approved LUC is valid for 24 months.
2. Construction Permit Once the Planning Permit is approved, a Construction Permit application (Form-301) is submitted with a full set of architectural, structural, plumbing, and electrical drawings, each signed by the relevant RAJUK-enlisted architect or engineer. The approved Construction Permit is valid for three years, within which construction must reach plinth level.
After construction is complete, a final Occupancy Certificate confirms the building is legally fit for use, valid for five years and renewable thereafter.
Because this process involves multiple government departments, strict document formatting requirements, and drawings that must be signed by RAJUK-registered professionals, most property owners in Dhaka choose to have an architecture firm manage the process rather than navigate it independently. We prepare every drawing to RAJUK's exact specification from the outset, so there's no back-and-forth between design revisions and approval submission.
Read our blogs related to RAJUK plan approval
Projects
Related Projects
What are the two main approvals needed from RAJUK?
A Planning Permit (Land Use Clearance), which confirms the land's approved use, and a Construction Permit, which approves the actual building design. Both are now submitted online through RAJUK's Electronic Construction Permitting System (ECPS).
How long does RAJUK plan approval take?
The Planning Permit stage typically takes around 30 days from submission. Construction Permit processing time varies by project scale and completeness of the submitted documents.
What documents are needed for RAJUK approval?
Common requirements include the land registry, mutation records, national ID or passport, updated land tax receipts, a digital land survey, and for the Construction Permit stage, signed architectural, structural, electrical, and plumbing drawings from RAJUK-registered professionals.
How long is an approved RAJUK plan valid for?
A Planning Permit (LUC) is valid for 24 months. An approved Construction Permit is valid for three years, within which construction must reach plinth level, or the approval becomes invalid.
Do I need an Occupancy Certificate after construction is finished?
Yes. After construction is complete, an Occupancy Certificate must be obtained from RAJUK before the building can legally be occupied. It's valid for five years and must be renewed afterward.
Can Level Seven handle the entire RAJUK approval process for me?
Yes. We manage document collection, drawing preparation, and submission through ECPS on the client's behalf, so the process requires minimal direct involvement from the property owner.
Blogs
From Our Blog
Guides, cost breakdowns, and design ideas for homeowners and builders in Bangladesh.









