RAJUK Building Approval Process 2026: Complete Step-by-Step Guide for Dhaka
Written and reviewed by Ishtiak Ahmed, Engineer, Level Seven
Building a home or a commercial property in Dhaka is a significant investment. But before construction begins, there is one thing that cannot be skipped: getting your building legally approved by RAJUK. Many people delay this step, underestimate it, or try to navigate it without proper guidance. The result is almost always the same: wasted time, unexpected costs and, in the worst cases, a building that cannot be sold, financed or legally occupied.
This guide explains how the RAJUK approval process works in 2026, updated for the Dhaka Metropolitan Building Rules 2025 (gazetted 14 December 2025), which replaced the 2008 rules.
RAJUK approval process at a glance
Step | Stage | Official time (2025 rules) | Realistic time | Validity |
|---|---|---|---|---|
1 | Planning Permit | 30 working days (45 for large or special projects) | 1 to 3 months | 2 years, renewable once for 1 year |
2 | Construction Permit | 45 days after all drawings are submitted | 2 to 6 months | 3 years (construction must reach plinth level) |
3 | Construction Start Notice | Filed in ECPS before work starts | Same day | Not applicable |
4 | Occupancy Certificate | Inspection within 15 working days, decision within 30 days | 1 to 2 months | No fixed expiry; renew only after a change of use, a deviation from the plan or disaster damage |
What RAJUK reports now: between March and September 2026, 7,055 Planning Permit applications were filed online and 5,393 approved, and 3,930 Construction Permit applications were filed and 2,600 approved. RAJUK has set a 30-day deadline for Planning Permits, and Construction Permit files must reach the Building Construction Committee within 24 days. Most remaining delays come from other agencies, such as the Fire Service and Civil Aviation, whose clearances are still handled on paper (RAJUK data reported by BSS, October 2026).
Why RAJUK approval matters
RAJUK is Dhaka’s principal building authority, responsible for all construction activity across the capital and its surrounding zones. The current area plan places roughly 1,528 square kilometres under its regulatory reach.
Any construction within this zone requires RAJUK’s approval before work starts. No exceptions, whether you are an individual building a family home or a developer putting up a multistorey apartment block.
What happens if you build without approval? The consequences are serious:
RAJUK has the authority to declare the structure illegal
Under the RAJUK Act 2026, building outside the approved design can mean up to 2 years in prison, a fine of up to Tk 50 lakh, or both
No bank in Bangladesh will offer a loan or mortgage on an unapproved building
Future flat sales and ownership transfers run into major legal problems
Permanent connections for water, gas, and electricity can be denied
The approval process takes time and patience. But building without it costs far more in the long run.
RAJUK goes digital: the ECPS system
One of the biggest changes in recent years is RAJUK’s shift to a fully digital platform called ECPS (Electronic Construction Permitting System). This is where applications are submitted, fees are paid and approvals are tracked from start to finish. Fees are paid online only, by mobile banking, card or net banking, and ECPS adds 15% VAT at payment. There is no bank draft or offline payment.
Portal address: ecps.gov.bd
Along with this shift came an official name change. The portal now uses Planning Permit instead of LUC, but they refer to the same thing. You will still come across the old name in older documents and conversations, so do not be confused when you see either one used.
The ECPS system has made the process more transparent and significantly reduced the need for in-person visits to RAJUK offices.
Full RAJUK approval process
Getting your building legally approved involves two back-to-back permits, followed by a final certification once construction is done.
Land Documents > Planning Permit > Architectural Design > Construction Permit > Construction Start Notice > Construction > Occupancy Certificate
Each stage builds on the previous one. You cannot jump ahead, and completing each step properly makes the next one much smoother.
Stage 1: Planning Permit (previously known as Land Use Clearance, LUC)
The Planning Permit is where everything begins. It is the official confirmation from RAJUK that your land is eligible for the type of construction you are planning. Until this permit is in your hand, nothing else can move forward.
Documents you need for the Planning Permit
Registered Deed (sale or inheritance)
Kharij or Mutation Certificate
CS, RS, SA, and BRS Land Records
Khatian and Dag Numbers
Latest Khajna (Land Tax) Receipt
Owner’s National ID
Owner’s photograph
Digital survey map with geo-coordinates at the plot corners
Allotment letter (for plots in a housing project) and NOCs such as CAAB, Fire Service or DoE, where they apply
Application Fee: Tk 5,000 under the 2025 rules (the same for a renewal or an appeal), paid online in ECPS, which adds 15% VAT
How this stage works
Submit the Planning Permit application online through the ECPS portal
RAJUK arranges a physical inspection of your site
A Town Planner reviews the inspection report and prepares a recommendation
If everything checks out, the Planning Permit is issued
Official processing time: 30 working days from submission (45 working days for apartment or real estate projects on more than 5 acres, block-based development and special buildings). Realistic timeline: 1 to 3 months in practice.
Validity: 2 years from the date the permit is issued
One thing many people do not know: if you need more time before submitting your Construction Permit, you can apply in ECPS to renew it once for 1 more year (fee Tk 5,000) before the original 2 years run out. If you miss this window, you will have to apply for the Planning Permit again.
Stage 2: Construction Permit (Building Plan Approval)
With the Planning Permit secured, you can now move into the design and technical submission phase. The Construction Permit is applied for in ECPS and requires a complete set of building drawings. Every set requires sign-off from a professional holding active RAJUK enlistment in that discipline.
The required drawing sets
Architectural Drawings, signed by a RAJUK-registered Architect
Structural Drawings, signed by a RAJUK-registered Structural Engineer
Plumbing Drawings, signed by a RAJUK-registered Plumbing Engineer
Electrical Drawings, signed by a RAJUK-registered Electrical Engineer
Mechanical Drawings (such as lifts, ventilation and air conditioning), where applicable
Fire Safety Drawings and the ECPS fire-safety (DCQR) checklists, where applicable
Other Construction Permit documents
Indemnity bond, for deep foundation, piling or basement work
Up-to-date income tax return slip
Agreement with your architect or engineer on Tk 300 non-judicial stamp paper
Up-to-date land tax receipt, and the plot joining map if plots are merged
Easement deed or NOCs where they apply (for example NHA or RAJUK Estate)
RAJUK enlistment certificate of the developer, if a developer is building
What the drawings must show
Site Plan at 1:4000 scale
Layout Plan at 1:200 scale, with room dimensions and door and window positions marked
All Floor Plans
Roof Plan
Front and Side Elevations
At least 2 Cross-Sections
Staircase Layout
Parking Plan
FAR and MGC Calculation Sheet
North arrow and road width
Planning Permit reference number and date
Occupancy type of the proposed building
CS, RS, SA Dag Number, Mouza, and Thana name
Official processing time: RAJUK’s Building Construction Committee decides within 45 days of receiving all drawings. Realistic timeline: 2 to 6 months. Fee: paid online after the committee recommends approval; Tk 50 per sqm of total floor area for homes and apartments, Tk 150 per sqm for offices and shops, plus VAT. Approved plan validity: 3 years. Construction must reach plinth level within this period.
Before you start building: file a Construction Start Notice in ECPS. Under the 2025 rules, “starting work” includes excavation, piling or foundation work.
Important rules under the 2025 building rules and DAP 2022-2035
The DAP 2022-2035 and the Dhaka Metropolitan Building Rules 2025 set the limits on what you can build. A design that does not comply will be rejected. The main ones:
Road width and FAR: your locality gives an Area FAR and your road width gives a plot FAR. The lower one is your base FAR, and incentives can raise it up to the higher one. Check yours with the free RAJUK FAR calculator.
Setbacks grow with height: the front must be at least 1.5 m from the boundary or 4.5 m from the road centre, whichever is more. Sides and rear are 1 m and 1.25 m up to 7 storeys, 1.25 m and 2 m for 8 to 10 storeys, and 3 m for 11 to 15 storeys.
Ground coverage depends on plot size: for example, a 5 katha plot may cover at most 62.5% and at least 46.5% of the land.
Corner plots: a 2 m × 2 m corner must be left open for the road.
Parking: each car space must be at least 2.4 m × 4.6 m. Driveways must be 3.5 to 4.25 m wide for one-way traffic, depending on the parking angle, and 4.25 m (about 14 ft) for two-way traffic.
Airport proximity and height: CAAB height clearance is required near flight paths, and a building 45.7 m or taller needs a red aviation warning light on top.
When your project is classified as a ‘Special Building’
Under rule 10 of the Dhaka Metropolitan Building Rules 2025, some projects are classified as Special Buildings. They no longer need a separate drawing approval, but the Building Construction Committee checks extra points (heritage, environment, traffic, flooding and utilities), the Planning Permit can take 45 working days, and more documents are needed.
Your project may fall into this category if it involves any of the following:
Any building with a gross floor area over 7,500 sqm
Any building with a direct connection to a national highway
A structure within 100 metres of a junction of two or more main roads named in the master plan
Any building for polluting or hazardous use (including brick fields) or for health care
A shopping centre with a gross floor area over 5,000 sqm
Any construction within 250 metres of a heritage building identified by the government, an environmentally critical area declared by DoE, or a riverbank
Any construction within 150 metres of a natural beauty area, forest or hill area identified in the master plan
If your project falls into any of these categories, identify it early. Special Buildings need extra documents, such as an easement deed for land given to the road, fire safety drawings, the Fire Service and Civil Defence NOC, the developer’s registration and other agency approvals that apply.
Extra clearances for large and special buildings
Under the Dhaka Metropolitan Building Rules 2025, extra clearances depend on where the plot is and whether the project is a Special Building (rule 10), not simply on how tall it is. Depending on the site, RAJUK may ask for:
CAAB height clearance near airport flight paths
A Fire Service and Civil Defence NOC and fire-safety drawings, which every Special Building needs
Department of Environment clearance and an environmental study, where applicable
A traffic study, or a Traffic Impact Assessment approved by the Dhaka Transport Coordination Authority, for projects that generate a lot of traffic
NOCs from the city corporation, Roads and Highways, BIWTA, the National Housing Authority or PWD, where the plot touches their land or roads
A Key Point Installation or heritage NOC near key installations or listed buildings
Electricity, water and gas connections are arranged separately with the utility companies, and a new connection needs the Occupancy Certificate.
Stage 3: Occupancy Certificate
Once construction is finished, the final step is applying in ECPS for the Occupancy Certificate. This certificate is RAJUK’s formal confirmation that the building has been constructed according to the approved plan. Under the 2025 rules, without it the building cannot get utility connections, and flats cannot be transferred or registered.
After your application is submitted, RAJUK inspects the building within 15 working days and decides within 30 days. If everything is in order, the Occupancy Certificate is issued. The fee is Tk 1,000. See our RAJUK Occupancy Certificate guide for the full process.
Do not treat the Occupancy Certificate as optional paperwork. Occupying or selling a building without it creates serious legal complications that are difficult and expensive to resolve later.
5 Mistakes that commonly cause delays or rejection
1. Land documents that are not fully in order Incomplete or unverified land records are the single most common reason applications get delayed. Get your mutation certificate, khajna receipts, and all CS/RS/SA records checked before you submit anything.
2. Working with professionals who are not RAJUK-registered Drawings signed by an architect or engineer without valid RAJUK registration will be rejected on the spot. Always verify registration status before engaging anyone for this work.
3. Designs that exceed FAR, setback, or MGC limits A design that pushes beyond the permitted FAR or does not respect required setbacks will not be approved, regardless of how well it is drawn up.
4. Missing the Planning Permit validity window You have 2 years to submit your Construction Permit after receiving the Planning Permit. If you need more time, apply in ECPS to renew it for 1 year before the deadline passes.
5. Not identifying Special Building requirements early enough A number of projects get caught off guard when they discover mid-process that their building is a Special Building with extra checks and documents. Check this at the very beginning.
More questions about RAJUK approval
Can I extend my Planning Permit if it is close to expiring? Yes. Before the 2-year validity runs out, you can apply in ECPS to renew it once for 1 year. If you miss this, you will need to apply for a fresh Planning Permit.
What is the difference between a Planning Permit and a Construction Permit? The Planning Permit confirms that your land is eligible for the kind of building you want to construct. The Construction Permit approves the actual design and drawings. You need both, and you need them in that order.
Do I need RAJUK approval for renovation work? Minor interior work typically does not require approval. However, any structural changes, additions to the building, or modifications to the exterior will require going through RAJUK.
How Level Seven Architecture and Construction handles the RAJUK approval process
At Level Seven, we manage the entire approval process on your behalf. This is not just about producing drawings. It is about making sure every document is right, every submission is compliant, and nothing gets missed that could slow things down or cause a rejection.
Here is what we take care of:
Reviewing and organizing all required land documents before submission
Producing fully RAJUK-compliant drawings across all required disciplines
FAR, setback, MGC, and density calculations in line with DAP 2022-2035
Coordinating structural, plumbing, electrical and mechanical drawings with enlisted engineers
Submitting all applications through the ECPS portal (Planning Permit, Construction Permit, Construction Start Notice and Occupancy Certificate)
Identifying any Special Building requirements or departmental clearances needed upfront
Managing revisions and resubmissions if required
For a consultation, WhatsApp us: +8801714302055
Getting RAJUK approval right the first time saves you months of back and forth. Every stage has a purpose, and every document on the checklist is there for a reason.
If you have questions about your specific plot or project, reach out. We are happy to help you understand exactly what your situation requires before you commit to anything.
Need help with RAJUK plan approval? Contact us about our RAJUK plan approval service.
Get Help With RAJUK Approval
Before you apply, check how many floors your plot allows with our free RAJUK FAR calculator. Our architectural design service in Dhaka prepares ECPS-ready drawings, and our RAJUK plan approval service handles documents, submission and follow-up for you.