RAJUK Occupancy Certificate in Dhaka 2026: Process, Documents, Fee and Renewal
Written and reviewed by Ishtiak Ahmed, Engineer, Level Seven
Your building is finished, but under RAJUK rules it is not legally ready to use until it has an Occupancy Certificate (OC), called বসবাস বা ব্যবহার সনদ in Bangla. Without it, the building cannot get new utility connections, and flats cannot be transferred or registered.
This guide explains how the OC works in 2026 under the Dhaka Metropolitan Building Rules 2025 (gazetted 14 December 2025), which replaced the 2008 rules. Some older guides, and even some old help pages, still say the OC must be renewed every 5 years. That is no longer the rule.
RAJUK Occupancy Certificate: key facts
Item | Under the 2025 rules |
|---|---|
Who issues it | RAJUK (the Authorized Officer), through ECPS |
When to apply | After construction is complete; a partial OC can be taken for a completed part of the building |
Fee | Tk 1,000 per application, paid online in ECPS (ECPS adds 15% VAT) |
Site inspection | Within 15 working days of applying |
Decision | Within 30 days of applying |
Validity | No fixed expiry |
Renewal | Only after a change of use, a deviation from the approved plan, or disaster damage (Tk 1,000) |
If rejected | Appeal within 30 days; the Appeal Committee decides within 30 days |
What is an Occupancy Certificate?
The Occupancy Certificate is RAJUK’s confirmation that the building was built according to its approved Construction Permit drawings and is fit to be used for its approved purpose. Under rule 22 of the 2025 rules, the OC counts as the final approval of the building.
It is the last of the RAJUK steps: Planning Permit, Construction Permit, Construction Start Notice, construction, then the Occupancy Certificate.
Why you need an OC
Rule 24 of the Dhaka Metropolitan Building Rules 2025 is clear about what you cannot do without an Occupancy Certificate:
No building, flat or space may be used for housing, business, industry or any other purpose
No new utility connection (electricity, gas, water) may be given to the building
No building or flat, in whole or in part, may be transferred, mutated (namjari) or registered
The building may only be used for the purpose written on the OC
The rules also say developers, real estate agents, mortgage lenders and anyone handling a sale must give the new owner or user a copy of the OC. In practice, banks also look for it before lending against a property.
When to apply
Apply once construction is complete. If you want to use part of the building first, for example the lower floors of an apartment building, the rules require a separate OC for that part.
During construction, RAJUK or its appointed inspector visits at least once at plinth level and once on each floor. Keeping your stage completion reports in order makes the final OC much easier.
Documents for the Occupancy Certificate
The ECPS checklist for the OC asks for:
Completion report
As-built architectural drawings
Structural drawings
All building-services designs (electrical, plumbing, mechanical and fire safety)
Under rule 22, the inspection also considers:
Stage completion reports at foundation, plinth, each floor and roof level
A supervision report and certificate, signed by the supervising architect or engineer (or the builder), confirming the work follows the approved plan
The as-built drawings, where the building differs from the drawings in any allowed way
Step by step: how the OC is issued
Apply in ECPS and pay the Tk 1,000 fee online.
Site inspection within 15 working days. The Authorized Officer inspects the building with you (or your representative) and your architect or engineer present.
Review. RAJUK checks the reports and documents for services, structural safety, fire safety and planning conditions.
Decision within 30 days of your application. If the OC is refused, RAJUK must give the reasons in writing.
Does an Occupancy Certificate expire?
No. Under the 2025 rules, the OC has no fixed validity period. Rule 25 says it must be renewed only in these cases:
The use of all or part of the building changes (for example, a flat turned into an office)
The building deviates from or changes the approved plan, other than through an approved plan revision
A disaster such as a fire or earthquake damages the structure or utility services, as confirmed by an architect or engineer
Renewal costs Tk 1,000. RAJUK inspects within 15 days and, if there are no deviations, renews the OC within the next 20 days. If it finds deviations, it rejects the application and lists them.
Do not ignore a renewal that is needed. Rule 26 makes the owner, the architect or engineer, and the responsible RAJUK officials liable if an OC is not renewed when one of these reasons applies.
What if the OC is rejected?
You can appeal to RAJUK’s Appeal Committee within 30 days of the rejection, with the appeal fee (Tk 5,000). The committee decides within 30 days. In complex cases it can ask the Urban Development Committee for a recommendation, which is given within 45 days.
Most rejections come from work that does not match the approved drawings: an extra floor, reduced setbacks, a covered parking area or a change of use. Fixing these before you apply is far cheaper than an appeal.
Buying a flat? Ask for the OC
Before you buy a flat or building in Dhaka, ask the seller or developer for a copy of the Occupancy Certificate along with the approved plan. Under the 2025 rules, a flat without an OC cannot be registered or transferred, and the building cannot get new utility connections. Compare the OC with what was built: the number of floors and the use must match.
Common mistakes that delay an OC
Building beyond the approved plan. Extra floors, rooftop rooms or reduced setbacks are the main reason OCs are refused.
Missing stage reports. Foundation, plinth, floor and roof completion reports should be prepared as the work goes, not at the end.
No supervising professional. The supervision certificate must be signed by the architect or engineer who supervised the work.
Using the building before the OC. Moving in, renting out or selling flats first puts you in breach of rule 24.
Changing use later without renewing. Turning a residential floor into a shop or office needs an OC renewal.
How Level Seven helps with the Occupancy Certificate
Our RAJUK plan approval service covers the whole journey, from the Planning Permit to the Occupancy Certificate. For the OC, we prepare the as-built drawings and completion documents, check the building against the approved plan before RAJUK’s inspection, and file and follow the application in ECPS.
If you are still planning, check how many floors your plot allows with our free RAJUK FAR calculator, so the building you design is one RAJUK will approve and certify.
Need help with an OC? Contact us or WhatsApp +8801714302055.