BOQ

What is a BOQ?

A BOQ (Bill of Quantities) lists every material and work item in your building with its quantity and price, so you know the total cost before construction starts.

A BOQ (Bill of Quantities) lists every material and work item in your building with its quantity and price,

Think of it like this: if you were baking a cake, the BOQ is the full recipe plus the price tag on every ingredient, written out so precisely that anyone could follow it and know exactly how much the cake will cost before they’ve bought a single egg. For a house in 2026, expect about ৳2,850 to ৳3,750 per sqft. Level Seven prepares an itemised BOQ from your drawings at current market rates.

Think of it like this: if you were baking a cake, the BOQ is the full recipe plus the price tag on every ingredient, written out so precisely that anyone could follow it and know exactly how much the cake will cost before they’ve bought a single egg. So you know the total cost before construction starts. For a house in 2026, expect about ৳2,850 to ৳3,750 per sqft. Level Seven prepares an itemized BOQ from your drawings at current market rates.

A BOQ is built in the same order the building is physically built

You cannot estimate a column’s cost before you know its foundation exists and how big it is. So the estimate follows the same order as the construction.

You cannot estimate a column’s cost before you know its foundation exists and how big it is. So the estimation sequence = the construction sequence.

Construction Sequence

01

Foundation

Piling - Pile cap - Ramp

01

Foundation

Piling - Pile cap - Ramp

02

Superstructure

Column - Beam - Slab - Repeat for all floors

02

Superstructure

Column - Beam - Slab - Repeat for all floors

03

Enclosure

Brickwork - Electrical - Plumbing

03

Enclosure

Brickwork - Electrical - Plumbing

04

Surface Finishing

Plaster - Door - Window - Tiles - Paint

04

Surface Finishing

Plaster - Door - Window - Tiles - Paint

05

Fixtures

Switches - Sockets - Sanitary - Lift - Generator - Substation - Pump

05

Fixtures

Switches - Sockets - Sanitary - Lift - Generator - Substation - Pump

06

External

Landscape - Feature Amenities - Beautification

06

External

Landscape - Feature Amenities - Beautification

Serial order to build a BOQ and estimation

BOQ and estimation calculation process: *

01.

boq and estimation

Get the drawings

architectural + structural

01.

boq and estimation

Get the drawings

architectural + structural

01.

boq and estimation

Get the drawings

architectural + structural

02.

boq and estimation

Piling

concrete + rebar quantity per pile → price it → × count → Piling total

02.

boq and estimation

Piling

concrete + rebar quantity per pile → price it → × count → Piling total

02.

boq and estimation

Piling

concrete + rebar quantity per pile → price it → × count → Piling total

03.

boq and estimation

Pile cap

same method as piling → Foundation total

03.

boq and estimation

Pile cap

same method as piling → Foundation total

03.

boq and estimation

Pile cap

same method as piling → Foundation total

04.

boq and estimation

Columns

floor by floor → Column total

04.

boq and estimation

Columns

floor by floor → Column total

04.

boq and estimation

Columns

floor by floor → Column total

05.

boq and estimation

Beams

floor by floor → Beam total

05.

boq and estimation

Beams

floor by floor → Beam total

05.

boq and estimation

Beams

floor by floor → Beam total

06.

boq and estimation

Slabs

floor by floor → Slab total

06.

boq and estimation

Slabs

floor by floor → Slab total

06.

boq and estimation

Slabs

floor by floor → Slab total

07.

boq and estimation

Brickwork

area → floor by floor → Brickwork total

07.

boq and estimation

Brickwork

area → floor by floor → Brickwork total

07.

boq and estimation

Brickwork

area → floor by floor → Brickwork total

08.

boq and estimation

Plaster

area → floor by floor → Plaster total

08.

boq and estimation

Plaster

area → floor by floor → Plaster total

08.

boq and estimation

Plaster

area → floor by floor → Plaster total

09.

boq and estimation

Doors/windows

count → Total

09.

boq and estimation

Doors/windows

count → Total

09.

boq and estimation

Doors/windows

count → Total

10.

boq and estimation

Tiles

floor, wall, toilet, kitchen, separately → Tiles total

10.

boq and estimation

Tiles

floor, wall, toilet, kitchen, separately → Tiles total

10.

boq and estimation

Tiles

floor, wall, toilet, kitchen, separately → Tiles total

11.

boq and estimation

Paint

area → Paint total

11.

boq and estimation

Paint

area → Paint total

11.

boq and estimation

Paint

area → Paint total

12.

boq and estimation

Electrical

circuits/fixtures + vendor equipment quotes → Electrical total

12.

boq and estimation

Electrical

circuits/fixtures + vendor equipment quotes → Electrical total

12.

boq and estimation

Electrical

circuits/fixtures + vendor equipment quotes → Electrical total

13.

boq and estimation

Plumbing

fixtures + pipe runs → Plumbing total

13.

boq and estimation

Plumbing

fixtures + pipe runs → Plumbing total

13.

boq and estimation

Plumbing

fixtures + pipe runs → Plumbing total

14.

boq and estimation

Lump-sum items

feature amenities, mobilization, admin/overhead

14.

boq and estimation

Lump-sum items

feature amenities, mobilization, admin/overhead

14.

boq and estimation

Lump-sum items

feature amenities, mobilization, admin/overhead

15.

boq and estimation

Sum everything

This is the Base Amount

15.

boq and estimation

Sum everything

This is the Base Amount

15.

boq and estimation

Sum everything

This is the Base Amount

16.

boq and estimation

Add contingency

Add it to the base amount

16.

boq and estimation

Add contingency

Add it to the base amount

16.

boq and estimation

Add contingency

Add it to the base amount

17.

boq and estimation

Find Cost/Sft

Divide the total amount by saleable area to find cost/sqft

17.

boq and estimation

Find Cost/Sft

Divide the total amount by saleable area to find cost/sqft

17.

boq and estimation

Find Cost/Sft

Divide the total amount by saleable area to find cost/sqft

Full building BOQ and cost estimation in Bangladesh

BOQ and construction cost estimation for a building in Dhaka
Construction materials quantity takeoff for a BOQ
Building under construction in Dhaka

Written and reviewed by Ishtiak Ahmed, Engineer, Level Seven

A BOQ (Bill of Quantities) from Level Seven Architecture & Construction lists every material, quantity, unit rate and labour cost in your building, stage by stage, so you know the real budget before construction starts and can compare contractor quotes line by line.

What is included in our BOQ and estimation service?

  • Quantity take-off from your architectural and structural drawings

  • Itemised rates for cement, rod, bricks, sand, stone chips, tiles, paint and fittings at current Dhaka market prices

  • Labour rates for each stage, from piling to finishing

  • Stage totals for foundation, superstructure, enclosure, finishing, electrical, plumbing and external works

  • Contingency, the base amount and the final cost per sqft of constructed and saleable area

  • A clear summary you can use to compare contractor quotes for the same drawings

Who needs a BOQ before construction?

  • Landowners building a house or apartment who want to control the budget from day one

  • Landowners and developers in a joint venture who need a reliable cost per sqft before agreeing on shares

  • Anyone comparing two or more contractor quotes for the same building

  • Families planning a duplex who want to see how finish choices change the total cost

What do you need from me to prepare a BOQ?

Your architectural and structural drawings, the finish level you want and the plot location. If you do not have drawings yet, our architectural design team can prepare them, and the BOQ follows the final design. Timing depends on the size of the building, and we confirm it once we see your drawings.

How is a BOQ calculated?

A BOQ follows the construction sequence shown above: each stage is measured from the drawings, priced and added up, then contingency is added and the total is divided by the area to get cost per sqft. The full method is below, stage by stage, with formulas, October 2026 rates and a worked example. For typical budgets, read house construction cost per sqft in Bangladesh for houses and apartment building construction cost in Dhaka for apartment buildings.

A BOQ (Bill of Quantities) from Level Seven Architecture & Construction lists every material, quantity, unit rate and labour cost in your building, stage by stage, so you know the real budget before construction starts and can compare contractor quotes line by line.

What is included in our BOQ and estimation service?

  • Quantity take-off from your architectural and structural drawings

  • Itemised rates for cement, rod, bricks, sand, stone chips, tiles, paint and fittings at current Dhaka market prices

  • Labour rates for each stage, from piling to finishing

  • Stage totals for foundation, superstructure, enclosure, finishing, electrical, plumbing and external works

  • Contingency, the base amount and the final cost per sqft of constructed and saleable area

  • A clear summary you can use to compare contractor quotes for the same drawings

Who needs a BOQ before construction?

  • Landowners building a house or apartment who want to control the budget from day one

  • Landowners and developers in a joint venture who need a reliable cost per sqft before agreeing on shares

  • Anyone comparing two or more contractor quotes for the same building

  • Families planning a duplex who want to see how finish choices change the total cost

What do you need from me to prepare a BOQ?

Your architectural and structural drawings, the finish level you want and the plot location. If you do not have drawings yet, our architectural design team can prepare them, and the BOQ follows the final design. Timing depends on the size of the building, and we confirm it once we see your drawings.

How is a BOQ calculated?

A BOQ follows the construction sequence shown above: each stage is measured from the drawings, priced and added up, then contingency is added and the total is divided by the area to get cost per sqft. The full method is below, stage by stage, with formulas, October 2026 rates and a worked example. For typical budgets, read house construction cost per sqft in Bangladesh for houses and apartment building construction cost in Dhaka for apartment buildings.

Planning the interior too?
Interior design costs BDT 70 per sq ft of agreed design area, with 2D and technical layouts, room-by-room 3D views, and an itemized BOQ. Execution is quoted separately.

Interior design

Planning the interior too?

Full interior design costs BDT 70 per sq ft of agreed design area. Execution is quoted separately from the agreed BOQ.

Interior design

Planning the interior too?

Full interior design costs BDT 70 per sq ft of agreed design area. Execution is quoted separately from the agreed BOQ.

How to calculate construction cost for each stage

Stage 1a: Piling Cost Calculation

Piling is the first item priced in most BOQs, since nothing else can be built until the foundation reaches ground strong enough to hold the structure. To calculate it, you need three inputs from the structural drawing: how many piles, what diameter, and what depth.

The volume of one pile is found with the standard cylinder formula: volume in cubic feet equals pi multiplied by radius squared multiplied by depth. Rebar weight inside that pile equals the number of bars multiplied by their length multiplied by the unit weight for that bar size.

Rebar unit weight follows a formula that works on any project, with any diameter. Weight in kilograms per metre equals the diameter in millimeters, squared, divided by 162. A 16mm bar, for example, works out to 16 squared divided by 162, which is 1.58 kg per metre, or about 0.48 kg per foot.

Concrete pricing is where most people get confused, since a rate like 360 or 370 taka per cubic foot does not come from nowhere. It is built from three raw materials. As an illustration, producing 100 cubic feet of finished concrete needs roughly 22.4 bags of cement at 535 taka per bag, which is 11,984 taka. It needs about 42 cubic feet of Sylhet sand at 58 taka per cubic foot, which is 2,436 taka. And it needs about 84 cubic feet of stone chips at 218 taka per cubic foot, which is 18,312 taka. Adding those together gives 32,732 taka in material cost, and dividing by 100 cubic feet gives roughly 327 taka per cubic foot.

Those same per cubic foot ratios apply to any project: about 0.22 bags of cement, 0.42 cubic feet of sand, and 0.84 cubic feet of stone chips, for every cubic foot of finished concrete. Normalised against each other, that works out to the 1:1.5:3 mix, the usual mix for columns, beams and slabs. A leaner 1:2:4 mix, used for lintels and base concrete, needs about 17.6 bags per 100 cubic feet. Cement is the smallest portion but the priciest per unit since it does the chemical binding. Stone chips are the largest portion since they are just structural bulk. Once material cost is set, a labour rate for pouring and compacting, typically 25 to 30 taka per cubic foot, and 3 to 5 percent for wastage, are added on top to reach an all in rate, commonly around 360 to 375 taka per cubic foot.

Here is a worked example. Take one pile, 2 feet in diameter and 60 feet deep. Volume comes to about 188 cubic feet. Material cost at 327 taka per cubic foot comes to about 61,480 taka. Adding labour at roughly 28 taka per cubic foot adds another 5,264 taka, giving about 66,700 taka for the concrete of that single pile. Add the rod, about 2.5 kilograms per cubic foot of pile concrete, so about 494 kilograms with wastage, costing about 52,900 taka, and boring labour of about 242 taka per running foot, about 14,500 taka. The complete pile then costs about 1.34 lakh taka. Multiply that by however many piles the drawing calls for.

Stage 1b: Pile Cap and Mat Foundation Cost Calculation

A pile cap sits on top of a cluster of piles and ties them together so the load from one column spreads evenly across all of them. A mat foundation does a similar job as one continuous slab, often used under a basement.

What you measure here is the length, width, and depth of the cap, since it is essentially a box shape. Concrete volume equals length multiplied by width multiplied by depth. Rebar weight equals the number of bars in each direction multiplied by their length multiplied by the unit weight for that diameter. Shuttering area, the surface the temporary mold has to cover, equals the perimeter of the cap multiplied by its depth.

Brick shuttering, commonly used underground since it does not need to be reusable, is priced in four steps that get added together. First, the number of bricks needed equals the shuttering area divided by 0.18, since that is roughly the surface one brick face covers. Second, brick material cost equals that brick count multiplied by about 13 taka per brick. Third, a small separate cost covers the mortar that binds the temporary brick wall together. Fourth, labour to build and later remove the shutter equals the area multiplied by about 15 taka per square foot. Steel shuttering, used later for columns, beams, and slabs, works differently. Because the same steel panels get reused hundreds of times across a building, it is priced as one flat all in rate per square foot, commonly 55 to 90 taka (around 60 for a house, more for steel shuttering on taller buildings), rather than broken into separate materials.

A few general values are worth remembering here. Rebar wastage allowance adds about 5 percent to the theoretical weight before pricing, to cover cutting loss and laps. Steel itself is not built up from ingredients the way concrete is, since it is a manufactured commodity bought at a market price, commonly 85 to 95 taka per kilogram in 2026. A separate labour charge of about 9 taka per kilogram covers cutting, bending, and tying it into place, giving an all in rebar rate of roughly 100 to 107 taka per kilogram.

For a worked example, take one pile cap measuring 6 feet by 6 feet by 2 feet deep. Concrete volume equals 6 times 6 times 2, which is 72 cubic feet, costing about 26,640 taka at 370 taka per cubic foot. For rebar, a pile cap typically holds about 4.4 kilograms of rod per cubic foot of concrete, so about 317 kilograms, or 333 kilograms with 5 percent wastage, costing about 35,600 taka at 107 taka per kilogram. Shuttering area equals the perimeter of 24 feet multiplied by the depth of 2 feet, which is 48 square feet, costing about 5,570 taka at 116 taka per square foot for brick shuttering. Adding all three brings the total for this one pile cap to roughly 67,800 taka.

Stage 2a: Column Cost Calculation

Columns carry every load above them down to the foundation, and they are the first thing built on each floor. What you measure is the cross section, such as 15 inches by 25 inches, the floor to floor height, and the rebar spec.

Concrete volume equals the width multiplied by the depth in inches, divided by 144 to convert into square feet, multiplied by the height in feet. Rebar weight follows the same bars times length times unit weight formula used everywhere else. Shuttering area equals the perimeter of the column’s cross section multiplied by its height.

Once that shuttering area is known, it gets reused twice more later in the project. Plaster cost equals that same surface area multiplied by about 25 to 38 taka per square foot, a rate that already bundles the cement sand mortar coat and the mason’s labour. Paint cost equals the same area multiplied by about 20 to 27 taka per square foot, bundling primer, two coats, and painter’s labour. The reason the same area shows up three times is simple: once concrete is cast and the shuttering removed, that exact surface is what later gets plastered, then painted.

A couple of general values matter here. Each main bar typically gets an extra 0.3 to 0.5 feet added for lap and anchorage, since bars are never cut to the exact theoretical length. And since every floor usually repeats the same column design, you only need to calculate one floor’s cost and multiply it by the number of identical floors.

As a worked example, take one column measuring 12 inches by 18 inches, 10 feet tall, with 8 main bars of 16mm. Volume equals 12 times 18 divided by 144, times 10, which is 15 cubic feet, costing about 5,550 taka. Rebar equals 8 times 10 times 0.48, which is 38.4 kilograms, costing about 4,109 taka. Shuttering equals a perimeter of 5 feet times the 10 foot height, which is 50 square feet, costing about 3,000 taka at 60 taka per square foot. Together, this one column costs roughly 12,700 taka.

Stage 2b: Beam Cost Calculation

Beams span between columns and carry the slab’s load sideways into them, and the calculation method mirrors columns closely, just horizontal instead of vertical. Concrete volume equals the width multiplied by the depth in inches, divided by 144, multiplied by the span length in feet. Shuttering area equals the beam’s exposed surfaces, meaning the bottom plus the two sides, multiplied by its length.

Rebar is more involved in beams than in columns, since a beam needs top bars, bottom bars, and small closed loops called stirrups spaced every few inches along its length, each calculated separately. This is exactly why beam quantity sheets in a real BOQ tend to be the longest and most detailed of all the structural sheets.

Pricing follows the same build up as columns: concrete at around 370 taka per cubic foot, rebar at around 107 taka per kilogram all in, and shuttering at around 60 taka per square foot for a house (80 to 90 for steel shuttering on taller buildings).

Stage 2c: Slab Cost Calculation

A slab becomes a floor or a roof, and it has the simplest volume calculation in the whole BOQ: area in square feet multiplied by thickness in feet.

Slab rebar is different from columns and beams, since it runs as a grid of bars in two directions rather than as individual bars. The number of bars across any span is found with a formula worth memorizing: span length in inches divided by bar spacing in inches, plus one. The plus one matters because spacing bars every 5 inches across a 20 inch span puts bars at 0, 5, 10, 15, and 20 inches, which is 4 gaps but 5 bars, since there is one at each end too.

Pricing uses the same three ingredients as before: concrete at around 370 taka per cubic foot and rebar at around 107 taka per kilogram, but slab shuttering can carry a higher rate, around 60 to 100 taka per square foot, since the soffit needs more temporary propping underneath than a column form does.

For a worked example, take a slab area of 500 square feet, 5 inches thick, which is about 0.42 feet, with bars spaced every 5 inches across a 20 foot span. Concrete volume equals 500 times 0.42, which is 210 cubic feet, costing about 77,700 taka. The number of bars across the span equals 20 times 12 divided by 5, plus 1, which comes to 49 bars. Shuttering cost equals 500 square feet times 60 taka, which is 30,000 taka.

Stage 3a: Brickwork Cost Calculation

Once the RCC frame is finished, brickwork fills in the walls that divide the building into rooms. Wall volume equals length multiplied by height multiplied by thickness, and brick count equals that volume divided by the space one brick plus its mortar joint occupies.

The wall rate is built from three parts added together. Brick material cost equals the number of bricks needed multiplied by about 13 taka per brick. Mortar cost, covering the cement and sand that binds the bricks, typically runs around 25 percent of the brick material cost. Mason labour equals the wall area multiplied by a labour rate of about 35 to 40 taka per square foot for a 5 inch wall. As a general value, one brick with its mortar joint takes up about 0.087 cubic feet, so a 5 inch wall needs about 5 bricks per square foot of wall and a 10 inch wall about 10. By volume, that is about 12 bricks per cubic foot, including breakage. All in, a 5 inch wall costs about 120 taka per square foot.

Stage 4a: Plaster Cost Calculation

Plaster area equals the wall or ceiling surface being covered, counting both faces if plastering happens on both sides. Pricing reuses the same rate mentioned under columns: about 25 to 38 taka per square foot all in, bundling the cement sand mortar coat with the labour to apply it, just now applied to brick walls instead of column surfaces.

Stage 4b: Doors, Windows, and Glazing Cost Calculation

This is the simplest calculation in the entire BOQ. Area equals width multiplied by height multiplied by count.

Pricing works differently here than for concrete or steel. Rather than building the rate up from raw ingredients, glazing and window rates are usually quoted directly by the aluminum or glass subcontractor as one bundled price per square foot, covering the frame, the glass, the hardware, and installation together. Commonly this lands somewhere between 480 and 560 taka per square foot depending on the glass and frame type, and you simply multiply that by the area.

Stage 4c: Tiles Cost Calculation

Tile area, whether for floors, walls, or toilets, equals the surface being covered as measured from the drawing, floor by floor. Pricing is shown as a material rate plus a labour rate added together. Floor tile commonly works out to about 100 to 140 taka material plus about 42 taka labour and the mortar bed, giving about 160 to 200 taka per square foot all in. Toilet or wall tile commonly runs about 85 taka material plus 42 taka labour, giving about 140 taka per square foot. A wastage allowance of 5 to 10 percent is standard, to cover cutting loss around edges and corners.

Stage 4d: Paint Cost Calculation

Paint area almost always reuses the same measurement taken for plaster, since it is the same wall or ceiling surface being finished. Pricing is quoted as one bundled rate, about 20 to 27 taka per square foot, covering putty, primer, two coats of paint, and labour.

Stage 5: Electrical and Plumbing Cost Calculation

Electrical and plumbing work differently from every stage before them. Instead of measuring length, width, and depth, you are counting circuits, fixtures, and pipe runs.

For electrical, cable is bought by the coil, a standard commercial spool length, rather than priced from raw copper. The number of coils needed equals the circuits per unit multiplied by the number of identical units, plus a small spare allowance, all doubled to account for the return run. Cable cost then equals that coil count multiplied by the price per coil, commonly about 4,100 taka for 1.5 rm cable up to about 9,300 taka for 4 rm cable. Big single items like the lift, generator, sub station, or solar setup are typically quoted directly by a vendor as a lump sum that bundles both supply and installation.

For plumbing, pipe cost equals the pipe length in running feet multiplied by a combined material and labour rate, for example around 50 taka material plus 20 taka labour per foot for a half inch pipe. When a pipe run crosses diagonally instead of running in a straight line, its true length is found using the Pythagorean theorem, the square root of one side squared plus the other side squared. Fixtures such as toilets and kitchen sets are priced as vendor quoted sets that already bundle in the installation labour.

Stage 6: Mobilization and Overhead Cost Calculation

This last stage is not calculated from drawings at all. Mobilization, site overhead, and admin costs are typically budgeted as lump sums or simple multipliers, such as staff salary multiplied by the number of months on site, or a flat percentage of the total construction cost. These are management costs running alongside the whole project timeline, not physical quantities you can measure from a drawing.

Full worked example: construction cost of a G+2 house

⚠️ This example prices a typical design at October 2026 market rates to show the complete flow from a bare plot to a final cost. It is a teaching example, not a real structural design. A real project needs an actual structural engineer’s drawing before any of these quantities can be trusted. To price your own house the same way, use the free house construction cost calculator.

The example building

  • Type: G+2 residential (Ground + 2 upper floors = 3 floors total)

  • Footprint: 30 ft × 40 ft = 1,200 sft per floor

  • Total constructed area: 1,200 × 3 = 3,600 sft

  • Saleable area: 3,200 sft

  • Foundation: 24 bored piles (1.5 ft dia, 30 ft deep) under 12 columns, joined by pile caps

RATES USED (October 2026)
Rate ItemRate (Tk)Unit
Concrete 1:1.5:3, site mixed (material + labour)369/cft
Rod, incl. cutting and binding107/kg
Brick shuttering (all-in)116/sft
Shuttering, columns, beams, slabs60/sft
5 inch brick wall (all-in)119/sft
Plaster, ½ inch (all-in)24/sft
Paint with putty (all-in)27/sft
Floor tile (all-in)198/sft
Toilet/wall tile (all-in)140/sft
Aluminium window (all-in)560/sft
FINAL COST
CategoryCost (Tk)
Base cost: materials, labour and fittings1,06,17,946
+ Site expenses (3%)3,18,538
+ Contingency (10%)10,93,648
COST IF YOU MANAGE THE BUILD (Tk)1,20,30,132
+ Contractor overhead and profit (15%)18,04,520
TURNKEY COST (Tk)1,38,34,652
COST PER SQFT
Per sqft of built area (3,600 sqft), self-managed3,342
Per sqft of built area, turnkey3,843
Per saleable sqft (3,200 sqft), self-managed3,759

Construction cost glossary: every term explained

Glossary: The Materials
TermWhat It Actually Is
ConcreteA mix of cement, sand, stone chips, and water. Once hardened, it is strong under pushing (compression) but weak under pulling or bending (tension).
Rebar / MS rod / ReinforcementSteel bars embedded inside concrete. Steel resists tension, which plain concrete lacks. Together they resist both pushing and pulling.
RCC (Reinforced Cement Concrete)Concrete with rebar inside. Used for anything carrying real structural load: columns, beams, slabs, pile caps, mat foundations.
CC / PCC (Plain/Cement Concrete)Concrete without rebar. Used where no structural strength is needed, such as a thin blinding layer poured before the real foundation.
Cement bagStandard unit of cement, always 50 kg per bag worldwide. Quantities are converted to number of bags for ordering.
BrickUsed two ways: as a wall material, or as a cheap, disposable mold for concrete called brick shuttering.
Glossary: The Shape-Making Step
TermWhat It Actually Is
Shuttering / FormworkConcrete is poured wet. It needs a mold to hold its shape until it cures. That mold is shuttering or formwork, removed once the concrete can hold itself up.
Steel shutteringReusable steel plate molds. More expensive per use, but very durable. Common for columns, beams, and slabs, since the same mold gets reused floor after floor.
Brick shutteringA temporary wall of bricks stacked around the concrete instead of a real mold. Removed, broken away, or left in place afterward. Cheaper than steel, so common underground for pile caps and foundations.
Glossary: Making Concrete, Two Methods
TermWhat It Actually Is
Manual mixingCement, sand, and stone chips mixed by hand or a small site mixer, right on the construction site.
RMC (Ready-Mix Concrete)Concrete mixed at a factory/batching plant to a precise, quality-controlled recipe, then delivered to site by mixer truck, ready to pour.
Why a BOQ compares bothRMC is usually more consistent and faster. But cost depends on site conditions, so it is sometimes cheaper than manual mixing, sometimes not. A good BOQ calculates both, so the estimator can pick whichever is cheaper.
Glossary: Structural Elements (in build order)
TermWhat It Actually IsWhy It Exists
PileA long, narrow RCC column driven/bored deep into the ground (sometimes 50-100+ ft).Used when surface soil is too weak to hold the building directly. Carries load down to stronger soil/rock far below.
Pile CapA thick RCC block cast on top of a cluster of piles (commonly 2-5 piles grouped).Ties the pile group together and spreads one column's load evenly across all piles below it.
Mat Foundation (Raft)One single, large, continuous RCC slab covering the whole building footprint, instead of many small foundations.Used where the whole building sits over a wide, evenly loaded area, such as under a basement. Spreads the load and resists water and uplift pressure.
BFS (Brick Flat Soling)A layer of bricks laid flat, side by side, on leveled/compacted earth.Poured before any concrete. Gives a stable, level working platform and a barrier against ground moisture.
ColumnA vertical RCC member.Carries the load of everything above (beams, slabs, walls) straight down to the foundation.
BeamA horizontal RCC member spanning between columns.Picks up the slab's load and carries it sideways to the nearest columns.
SlabA flat, horizontal RCC surface.The actual floor you walk on, or the roof. Rests on the beams.
Retaining wallA wall designed to hold back earth on one side (commonly around a basement).Keeps surrounding soil from collapsing into the excavated basement space.
Glossary: After The Structural Frame Is Finished
TermWhat It Actually Is
BrickworkNon-load-bearing walls built with brick + mortar, filling the spaces of the completed RCC frame to create rooms.
PlasterA thin cement-sand coating applied over brick/concrete surfaces (inside and outside) to smooth them before tiling or painting.
Rough-in (electrical/plumbing)Pipes and electrical wiring embedded inside walls before plaster covers them. Has to happen at a specific point in the sequence.
FinishingGeneral term for everything that makes a space livable/presentable: floor/wall tiles, paint, doors, windows, cladding, hardware.
Glossary: The Math and Estimation Vocabulary
TermWhat It Actually Is
Quantity TakeoffThe very first step of any estimate: measuring from drawings exactly how much of each item is needed (cft of concrete, kg of steel, sft of tiles, etc.).
Unit rateThe price of one unit of something. Tk/cft for concrete, Tk/kg for steel, Tk/sft for tiles, Tk/bag for cement.
Cost formula (repeats everywhere)Total Cost = Quantity x Unit Rate. Every single BOQ line, however complex it looks, boils down to this.
Wastage / AllowanceA small % added on top of the theoretical quantity, because real-world work always loses some material to cutting, spillage, laps. Commonly 5-10% for rebar, similar for tiles/bricks.
Rate analysisWorking out from first principles what it costs to produce one unit of a finished item, like one pile cap or one cft of finished RCC. Material and labour bundled into one number.
Glossary: Units You'll See Constantly (Bangladesh Convention)
UnitWhat It MeasuresUsed For
cft (cubic feet)VolumeConcrete, earthwork, excavation
sft (square feet)AreaShuttering, tiles, plaster, paint, glass
rft (running feet)LengthPipes, beams, sheet piles
kg / tonWeightSteel/rebar (1 ton = 1000 kg)
bagCementAlways 50 kg/bag
kathaLand area (BD-specific)~720 sq ft, used for plot size
nosCountDoors, windows, piles, fixtures. Anything counted as whole units.

FAQs

Frequently Asked Questions

What does a construction cost estimate from Level Seven include?

It's broken down by foundation, superstructure, finishing, electrical, plumbing, and site preparation costs, giving a category-by-category view of where the budget goes rather than a single lump-sum figure.

Can I use a BOQ to compare contractor quotes?

Yes. When every contractor prices the same itemised list, you compare rates line by line instead of lump sums, and you can see which items a quote has left out or priced too low. The same BOQ then works as a checklist for paying the contractor stage by stage.

Blogs

From Our Blog

Guides, cost breakdowns, and design ideas for homeowners and builders in Bangladesh.

Get Started

Ready to start your project?

Get in touch today and let's discuss your project

Get Started

Ready to start your project?

Get in touch today and let's discuss your project

Get Started

Ready to start your project?

Get in touch today and let's discuss your project